January 27, 2026 Forklift Furnace Project Progress Update
Project Overview
The forklift furnace project is advancing steadily as planned. All key components have entered the final stage of assembly, and we are on track to meet the scheduled milestones. Below is a detailed update on the current progress and subsequent schedule.
Component Progress
Furnace Body: Fully fabricated, assembled and passed quality inspection.

Furnace Door: Awaiting the finished machined parts for assembly; modifications to the furnace door design compare with the one on drawing

Forklift Furnace Work in progress
Forklift: Integrated with the furnace system, and lifting-positioning functions calibrated.

Forklift Work in progress

Furnace Forklift Furnace
Water Tank: Installed; waiting for the water leakage test to be conducted.

Forklift Furnace Quenching Tank Work in progress

Forklift Furnace Work in progress
Subsequent Schedule
Overall Completion: The entire forklift furnace system is expected to be fully completed within one week (by February 3, 2026).
Electrical Installation: Electrical wiring, control system installation and debugging are scheduled to be finished within three weeks (by February 17, 2026).
CE Certification: After the completion of electrical installation, we will submit the application for CE certification immediately. The certification process will be promoted in an orderly manner to ensure compliance with European standards.
Project Outlook
The project team is committed to ensuring the quality and progress of the work. We will closely monitor each subsequent link, proactively address potential issues, and strive to deliver the qualified forklift furnace to customers as scheduled. We will keep you updated on any major progress in a timely manner.

Zhejiang Wannengda Furnace Industry Co., Ltd.