“Run one part and see” is how acceptance fights start: surveying a car bottom furnace properly
We’ve sat through enough acceptance meetings to know how fights start: somebody says “run one part and see.” One good part tells you almost nothing about the furnace – it tells you about that part, in that position, on that day. What actually proves a car bottom furnace is a temperature-uniformity survey of the effective heating zone, done to a written method, with numbers both parties sign. In China that method is GB/T 9452; if you work to AMS 2750 pyrometry, the thinking will feel instantly familiar – different letters, same discipline.
The parameter checklist
| Parameter | What to check | How |
|---|---|---|
| Uniformity | Max deviation from setpoint across the effective heating zone | The survey – this is the headline |
| Control accuracy | Instrument class, thermocouple grade, calibration in date | Certificates, on the table |
| Lining | Module packing, anchors, no cracks or shedding | Eyes + the technical agreement |
| Car & seals | Smooth travel; door and car seal contact | No-load run |
| Ramp | Time-to-temperature on an empty furnace | Recorded curve |
| Safety interlocks | Over-temp alarm, door interlock; gas units – leak alarm and flame safeguard | Function tests, witnessed |
| Paper | Certificates, calibration records, drawings, manual, spares list | Checklist against the contract |
The survey, step by step
① Lay survey thermocouples through the effective heating zone – positions and counts per the standard and the furnace class. ② Calibrated thermocouples only, into a multi-point recorder. ③ Soak at setpoint, empty or loaded as agreed, and record the field. ④ Read each point’s maximum deviation; that set of numbers is the uniformity class. ⑤ Both parties sign the report; it becomes the acceptance record and your baseline for future surveys.
Have a competent third party run it, or run it jointly with the manufacturer. What you should never do is let the seller survey alone and hand you a certificate – not because vendors lie, but because a shared measurement is a shared understanding.
Contract clauses worth fighting for
① The uniformity class and the standard it’s surveyed to. ② The remedy if the class isn’t met – rectify and re-survey, or return. ③ Empty-furnace ramp time. ④ A surface temperature-rise limit. ⑤ After-sales response time and spares availability in years. ⑥ Payment milestones tied to acceptance, not to shipment. Verbal promises are not acceptance criteria; we put that sentence in our own contracts.
FAQ
What should acceptance of a car bottom furnace actually cover?
The uniformity survey plus control accuracy, lining, car and seals, ramp, safety interlocks and documentation – against the contract, line by line.
Who should run the uniformity survey?
A qualified third party, or supplier and buyer jointly. Signed numbers, stored with the furnace’s file – that report is your baseline at every future survey.
When we commission a furnace, the survey report is part of the delivery – and our service crews commit to reaching most sites within 48 hours. Car bottom furnace range; questions to wndfurnace@aliyun.com.