“Run one part and see” is how acceptance fights start: surveying a car bottom furnace properly

We’ve sat through enough acceptance meetings to know how fights start: somebody says “run one part and see.” One good part tells you almost nothing about the furnace – it tells you about that part, in that position, on that day. What actually proves a car bottom furnace is a temperature-uniformity survey of the effective heating zone, done to a written method, with numbers both parties sign. In China that method is GB/T 9452; if you work to AMS 2750 pyrometry, the thinking will feel instantly familiar – different letters, same discipline.

The parameter checklist

Parameter What to check How
Uniformity Max deviation from setpoint across the effective heating zone The survey – this is the headline
Control accuracy Instrument class, thermocouple grade, calibration in date Certificates, on the table
Lining Module packing, anchors, no cracks or shedding Eyes + the technical agreement
Car & seals Smooth travel; door and car seal contact No-load run
Ramp Time-to-temperature on an empty furnace Recorded curve
Safety interlocks Over-temp alarm, door interlock; gas units – leak alarm and flame safeguard Function tests, witnessed
Paper Certificates, calibration records, drawings, manual, spares list Checklist against the contract

The survey, step by step

① Lay survey thermocouples through the effective heating zone – positions and counts per the standard and the furnace class. ② Calibrated thermocouples only, into a multi-point recorder. ③ Soak at setpoint, empty or loaded as agreed, and record the field. ④ Read each point’s maximum deviation; that set of numbers is the uniformity class. ⑤ Both parties sign the report; it becomes the acceptance record and your baseline for future surveys.

Have a competent third party run it, or run it jointly with the manufacturer. What you should never do is let the seller survey alone and hand you a certificate – not because vendors lie, but because a shared measurement is a shared understanding.

Contract clauses worth fighting for

① The uniformity class and the standard it’s surveyed to. ② The remedy if the class isn’t met – rectify and re-survey, or return. ③ Empty-furnace ramp time. ④ A surface temperature-rise limit. ⑤ After-sales response time and spares availability in years. ⑥ Payment milestones tied to acceptance, not to shipment. Verbal promises are not acceptance criteria; we put that sentence in our own contracts.

FAQ

What should acceptance of a car bottom furnace actually cover?
The uniformity survey plus control accuracy, lining, car and seals, ramp, safety interlocks and documentation – against the contract, line by line.

Who should run the uniformity survey?
A qualified third party, or supplier and buyer jointly. Signed numbers, stored with the furnace’s file – that report is your baseline at every future survey.

When we commission a furnace, the survey report is part of the delivery – and our service crews commit to reaching most sites within 48 hours. Car bottom furnace range; questions to wndfurnace@aliyun.com.